Q: Pick up the correct statement from the following:
Option | Answer | Is Correct |
---|---|---|
1 | The float may be positive, zero or negative | |
2 | If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed | |
3 | If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project | |
4 | All the above |